Case History
Client
Ferrero Group
Project
Demolition works, construction of new compartmentalization works, installation of process machinery, MEP systems, and utilities.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Alba - Cuneo
Status
Ongoing
Client
Ferrero Group
Project
Relocation of underground services, excavation works with archaeological assistance, construction of Reinforced Concrete tanks, and installation of systems.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Ongoing
Client
Ferrero Group
Project
Installation of a sprinkler system inside operational industrial buildings.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Alba - Cuneo
Status
Completed
April 2018 – October 2025
Client
Ferrero Industriale Italia S.r.l. – Ferrero Group
Project
Micropiles, trench excavations, steel columns and beams, finishes, and MEP systems.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana – Milan
Status
Completed
April 2021 – March 2024
Client
Ferrero Group
Project
Construction of a new sprinkler system inside operational industrial buildings.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Sant’Angelo dei Lombardi - Avellino
Status
Completed
March 2022 – May 2024
Client
Ferrero Group
Project
Construction of a new industrial building and systems. Excavation works, Reinforced Concrete foundations, prefabricated structure, MEP systems, and special systems.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
February 2022 – December 2024
Client
Ferrero Group
Project
Expansion of the storage area. Relocation of underground services, excavation works, construction of a containment basin for silo leakage, steel structure, and roofing panels.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
April 2021 – March 2023
Client
Ferrero Group
Project
Construction of a new industrial building and installation of process machinery. Special foundations, excavation works, Reinforced Concrete foundations, prefabricated structure, MEP systems, and special systems.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Balvano – Potenza
Status
Completed
March 2021 – December 2023
Client
Ferrero Group
Project
Construction of a new industrial building designed for the installation of mechanized storage and material loading systems. Reinforced Concrete foundations, prefabricated structure, MEP systems, and special systems.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Balvano – Potenza
Status
Completed
March 2021 – May 2023
Client
Ferrero Group
Project
Removal of process machinery, MEP systems, and compartmentalization works.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Balvano - Potenza
Status
Completed
January 2021 – May 2022
Client
Ferrero Group
Project
Construction of an expansion in steel structure, insulated facade panels, MEP systems, utilities, and process machinery.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Balvano - Potenza
Status
Completed
January 2020 – April 2022
Client
Ferrero Group
Project
Removal of process machinery, process systems, utilities, and compartmentalization works. New compartmentalization works, utility systems, process machinery, process systems, and finishes.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
March 2020 – April 2022
Client
Ferrero Group
Project
Relocation of underground services, excavation works, construction of a containment basin for silo leakage, steel structure, and roofing panels.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
March 2020 – April 2022
Client
Ferrero Group
Project
Construction of a new steel structure, installation of process machinery, special systems, and utilities.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Sant’Angelo dei Lombardi - Avellino
Status
Completed
February 2021 – April 2022
Client
Ferrero Group
Project
Excavation works, Reinforced Concrete works, construction of a steel structure, facade and roofing panels, installation of racking systems, utilities, special systems for automated warehouse, and finishes.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
February 2019 – May 2022
Client
Ferrero Group
Project
Relocation of underground services, excavation works, steel structure, and roofing sheets.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
February 2021 – December 2022
Client
Ferrero Group
Project
Internal demolition works, new compartmentalization works, and MEP systems.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
April 2021 – December 2022
Client
Ferrero Group
Project
Strip-out works, installation of heavy steelwork, facade panels, load-bearing slab, MEP systems, finishes, and fit-out.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
February 2019 – May 2021
Client
Ferrero Group
Project
Strip-out works, installation of heavy steelwork, facade panels, load-bearing slab, MEP systems, finishes, and fit-out.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
February 2019 – May 2021
Client
Ferrero Group
Project
Compartmentalization works, utilities, installation of process machinery, process systems, utilities, and finishes.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Alba - Cuneo
Status
Completed
April 2020 – October 2021
Client
Ferrero Group
Project
Demolition works, Reinforced Concrete works, construction of a steel structure, facade and roofing panels, installation of racking systems, utilities, special systems for automated warehouse, and finishes.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Alba - Cuneo
Status
Completed
February 2019 – October 2021
Client
Vailog S.r.l.
Project
Excavation works, foundations, prefabricated structures, internal compartmentalization works, MEP systems, and finishes.
Professional service
HSE.
Location
Novara
Status
Completed
February 2020 – October 2021
Client
Ferrero Group
Project
Excavation works, Reinforced Concrete structure, facade and roofing panels, installation of transformers, MEP systems, and special systems.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
March 2018 – April 2020
Client
Ferrero Group
Project
Construction of a new sprinkler system inside operational industrial buildings.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Balvano - Potenza
Status
Completed
March 2019 – May 2020
Client
Ferrero Group
Project
Demolition works, Reinforced Concrete works, construction of a steel structure, facade and roofing panels, installation of racking systems, utilities, special systems for automated warehouse, and finishes.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Arlon - Belgium
Status
Completed
February 2019 – December 2020
Client
Ferrero Group
Project
Demolition works, construction of new compartmentalization works, installation of process machinery, MEP systems, and utilities.
Professional service
HSE.
Location
Villers Écalles - France
Status
Completed
February 2019 – December 2020
Client
Cesare S.p.A. - Bosch Group
Project
Extraordinary maintenance. Strip-out works, internal demolition works, new compartmentalization works, MEP systems, and finishes.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Villasanta – Monza Brianza
Status
Completed
April 2017 – November 2018
Client
Impresa ICM SpA
Project
Excavation works, foundations, prefabricated concrete structure, facade and roofing panels, internal compartmentalization works, MEP systems, and finishes.
Professional service
HSE.
Location
Fossoli - Modena
Status
Completed
April 2017 – December 2018
Client
Ferrero Group
Project
Installation of machinery and special systems.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
June 2018 – December 2018
Client
Ferrero Group
Project
Excavation works, foundation piles, special systems, and finishes.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
March 2017 – December 2018
Client
Ferrero Group
Project
Removal of process machinery, process systems, utilities, and compartmentalization works. New compartmentalization works, utility systems, process machinery, process systems, and finishes.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
February 2017 – December 2018
Client
Ferrero Group
Project
Removal of process machinery, process systems, utilities, and compartmentalization works. New compartmentalization works, utility systems, process machinery, process systems, and finishes.
Professional service
Works Manager - Safety Coordinator during the Design and Construction Phases.
Location
Pozzuolo Martesana - Milan
Status
Completed
February 2016 – December 2017
Client
Ferrero Group
Project
Internal demolition works and MEP system modifications.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Caprarola - Viterbo
Status
Completed
March 2015 – April 2016
Client
Ferrero Group
Project
Demolition works, construction of a steel structure, MEP systems, and finishes.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Caprarola - Viterbo
Status
Completed
March 2015 – April 2016
Client
Acea Distribuzione S.p.A.
Project
Maintenance of the former building used for core lifting operations for the testing and inspection facilities Strip-out works, internal demolition works, new compartmentalization works, MEP systems, and finishes.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Rome
Status
Completed
March 2015 – April 2016
Client
Ferrero Group
Project
Trench excavations, installation of piping and fire hydrants.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Caprarola - Viterbo
Status
Completed
March 2015 – December 2015
Client
Ferrero Group
Project
Removal of systems, installation of utilities, installation of shelling machines, special systems, and finishes.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Caprarola - Viterbo
Status
Completed
February 2015 – December 2015
Client
Ferrero Group
Project
New food line. Construction of a steel structure, facade and roofing panels, internal compartmentalization works, MEP systems, and finishes.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Alba - Cuneo
Status
Completed
February 2018 – December 2020
Client
Ferrero Group
Project
Installation of seismic elements, demolition works, steel structure, facade and roofing panels, internal compartmentalization works, MEP systems, and finishes.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Alba – Cuneo
Status
Completed
February 2018 – December 2019
Client
Ferrero Group
Project
Compartmentalization works, utilities, installation of process machinery, process systems, and finishes.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Alba – Cuneo
Status
Completed
February 2018 – December 2018
Client
Ferrero Group
Project
Excavation works, foundations, heavy steelwork, MEP systems, and special systems.
Professional service
Safety Coordinator during the Design and Construction Phases.
Location
Alba – Cuneo
Status
Completed
February 2017 – December 2017